Judgment:
[With WP (C) Nos. 269/2006, 598/2006, 29/2007, 35/2007 and 53/2007]
R. V. Raveendran, J
1. This appeal by Special Leave is filed against the order dated
11.04.2002, passed by the National Consumer Dispute Redressal Commission
('Commission' for short) in O.P.No. 21 of 1995.
The Facts
2. The Banglore Development Authority (Appellant herein, 'BDA' for
short) introduced a "Self Financing Housing Scheme" for construction of
flats/houses in Banglore in the year 1982. The said Scheme contemplated
construction of three types of flats/houses categorized as Higher Income
Group, Middle Income Group, and Low Income Group ('HIG', 'MIG', and 'LIG'
for short). Under the said scheme an applicant for allotment was
required to make an initial deposit of 15% of the cost of the unit and
pay the balance in eight quarterly instalments of 10% and the last
instalment of 5%.
3. Syndicate Bank ('Respondent'
herein) made an application dated 17.7.1982 for allotment of 250
flats/houses under the said scheme, that is, 15 'HIG' Houses, 110 'MIG'
units and 125 'LIG' units. BDA registered the request for allotment of
15 HIG Houses, vide confirmation letter dated 20.8.1984. This appeal
relates to delay in delivery of 11 HIG houses at R.M.V. Extension,
Bangalore.
4. BDA had initially fixed the
tentative price of a HIG house as Rs.2,85,000/-. The price was revised
to Rs.4.75 lakhs per unit (Rs.5.5 lakhs in respect of corner units). By
letter dated 22.08.1985, BDA informed the respondent about the revision
of price of HIG Houses from Rs.2.85 lakhs to 4.75 lakhs per unit. BDA
also indicated the total amount due in respect of 15 HIG Houses and
required the Respondent to pay the said amount in installments as shown
in the Annexure thereto. BDA also informed the Respondent that the units
would be ready for occupation in December, 1986. As respondent did not
pay the instalments, BDA sent a letter dated 20.10.1986 demanding
payment. By letter dated 27.5.1987, BDA informed Respondent that 15
Houses (including three corner houses) had been allotted to Respondent
on 16.1.1987 and furnished the numbers of the houses allotted.
5. A sum of Rs.98,85,210/- paid by
the Respondent towards the cost of LIG units became refundable to
respondent, on account of surrender of allotment of the 125 LIG units.
The cost of 15 HIG houses was Rs.73.5 lakhs (that is, three corner units
at the rate of Rs.5.5 lakhs each and 12 other units at the rate of
Rs.4.75 lakhs each). The respondent had paid a sum of Rs.19,33,925/- in
advance towards the cost of the 15 H.I.G. houses and the balance due was
Rs.54,16,075/-. By letter dated 15.5.1989, BDA adjusted and appropriated
the said sum of Rs.54,16,075/- (due in respect of 15 HIG Houses) and a
sum of Rs.21,66,250/- (due in respect of MIG Units), from out of
Rs.98,85,210/- paid towards LIG units, and refunded the balance of
Rs.23,02,885/- to the Respondent. Thus it would be seen that the cost of
H.I.G. units was received by BDA only on 15.05.1989.
6. BDA delivered 4 HIG houses in
December, 1989 and May, 1990. The completion of construction and
delivery of remaining 11 H.I.G. houses (in RMV Extension, Bangalore) was
delayed. By letters dated 29.11.1989, 17.01.1990, 9.7.1993 and
11.1.1994, the Respondent pointed out the delay in delivery of the HIG
houses and requested for early delivery of possession of the houses.
Respondent also demanded interest on the price paid, at the bank rate
from 01.01.1986 till date the delivery of the houses apart from
reimbursement of the losses incurred on account of the non-delivery.
When the officers of the respondent met the officers of BDA personally
to enquire about the 11 Houses, they were informed that the delay was on
account of the contractor (M/s. Khoday Engineering) raising a dispute
and stopping the work in respect of part of the project, and assured
that possession will be delivered immediately after completion. The
Respondent issued a final notice dated 11.07.1994 through counsel
demanding performance within one month. When BDA failed, the respondent
filed a complaint before the Commission under section 21 of Consumer
Protection Act, 1986 ('Act' for short).
Claim, defence and the decision
7. The Respondent sought the
following reliefs against BDA, in its complaint :
a) Completion and due delivery of the remaining 11 HIG houses;
b) Payment of Rs.1,98,40,930/73 by
way of interest on the sum of Rs.53 lakhs being the price of the said 11
houses from 01.01.1986 to 31.12.1994 (the interest claimed at the bank
rate varying from 16.5% to 24.25% P.A. compounded quarterly);
c) Payment of Rs. 16.5 lakhs as
reimbursement of the rent paid by the Respondent for 11 houses at the
rate of Rs.3,000/- per house per month from 01.01.1987 to 31.12.1994
(Note : Though for 96 months the amount works out Rs.31,68,000/-, claim
was restricted to Rs.16.5 lakhs which is the rent for 11 houses for 50
months);
d) Payment of Rs.25,00,000/- as
compensation for mental agony and harassment;
e) Payment of future interest at
19.5% P.A. on Rs. 53,00,000/- plus Rs.33,000/- per month by way of
reimbursement of the rent, from 01.01.1995 till delivery of possession
8. BDA resisted the claim both on
the question of maintainability, as also merits. In brief, the
contentions were :
a) It was not a service provider nor a seller of goods and the
respondent was not a 'consumer' and therefore the complaint under the
Act was not maintainable.
b) The contract did not stipulate
any period for completion and delivery. Being a building contract, time
was not the essence of the contract. The project related to construction
of 558 HIG Houses. 490 houses were completed during 1989. The contractor
- M/s. Khoday Engineering, raised a dispute and delayed the work
relating to the remaining 68 houses (including 11 houses to be delivered
to the respondent). After making all possible efforts to persuade the
contractor to take up and complete the work, it rescinded the contract
with the contractor by Resolution dated 15.2.1995 and took steps to get
the work completed through an alternative agency. The delay was thus for
reasons wholly beyond its control and unintentional, and there was no
breach.
c) It would complete and deliver the
11 houses within a short time at the agreed price, though price of the
houses had risen by 10 times.
d) As it was executing the self
financing housing scheme on 'no profit no loss' basis, it should not be
burdened with any financial liability for any delay.
e) Even if it was treated as a
service provider and the complaint was held to be maintainable, as there
was no negligence or deficiency in service on its part, it was not
liable to pay any interest or compensation.
9. During the pendency of the
complaint before the commission, BDA delivered one HIG house on
21.1.1997 and remaining 10 HIG houses on 12.3.1997. The Respondent thus
secured the main relief sought in the complaint. What remained was the
claim for interest and compensation. Parties led evidence by way of
affidavits. Neither party sought leave to cross-examine the witness
(deponent) of the other party. The Commission by order dated 11.04.2002
allowed the complaint. It held:
a) BDA had promised to deliver the
houses to the Respondent by December, 1986.
b) In spite of respondent having
made full payment and making repeated demands, 11 houses were not
delivered till the complaint was filed in 1995. Thus there was
deficiency of service on the part of BDA.
c) BDA had not placed any material
on record to show why the houses could not be completed and delivered
between 1985 to 1991. The complainant was in no way concerned with the
dispute between BDA and its contractor and the consequential delay. Even
though the 11 houses were delivered in 1997 after the complaint, BDA was
guilty of deficiency in rendering service.
In view of the said findings,
following its decision in HUDA Vs. Darsh Kumar [Revision Petition No.
1197/1998 dated 31.8.2001], it directed the appellant to pay interest at
18% per annum on Rs.53,00,000/- (the approximate price of 11 HIG Houses)
commencing from the expiry of two years after the deposit of last
instalment of Rs.53 lakhs up to date of handing over the possession. The
said order is challenged in this appeal.
The
principles
10. Where a Development Authority forms layouts and allots plots/flats
(or houses) by inviting applications, the following general principles
regulate the granting of relief to a consumer (applicant for allotment)
who complains of delay in delivery or non-delivery and seeks redressal
under the Consumer Protection Act, 1986 ('Act' for short) - [vide :
Lucknow Development Authority vs. M. K. Gupta - 1994 (1) SCC 243,
Ghaziabad Development Authority vs. Balbir Singh - 2004 (5) SCC 65, and
Haryana Development Authority vs. Darsh Kumar - 2005 (9) SCC 449, as
also Ghaziabad Development Authority vs. Union of India - 2000 (6) SCC
113]:
(a) Where the development authority
having received the full price, does not deliver possession of the
allotted plot/flat/house within the time stipulated or within a
reasonable time, or where the allotment is cancelled or possession is
refused without any justifiable cause, the allottee is entitled for
refund of the amount paid, with reasonable interest thereon from the
date of payment to date of refund. In addition, the allottee may also be
entitled to compensation, as may be decided with reference to the facts
of each case.
(b) Where no time is stipulated for
performance of the contract (that is for delivery), or where time is not
the essence of the contract and the buyer does not issue a notice making
time the essence by fixing a reasonable time for performance, if the
buyer, instead of rescinding the contract on the ground of
non-performance, accepts the belated performance in terms of the
contract, there is no question of any breach or payment of damages under
the general law governing contracts. However, if some statute steps in
and creates any statutory obligations on the part of the development
authority in the contractual field, the matter will be governed by the
provisions of that statute.
c) Where an alternative site is
offered or delivered (at the agreed price) in view of its inability to
deliver the earlier allotted plot/flat/house, or where the delay in
delivering possession of the allotted plot/flat/house is for justifiable
reasons, ordinarily the allottee will not be entitled to any interest or
compensation. This is because the buyer has the benefit of appreciation
in value.
(d) Though the relationship between
Development Authority and an applicant for allotment is that of a seller
and buyer, and therefore governed by law of contracts, (which does not
recognise mental agony and suffering as a head of damages for breach),
compensation can be awarded to the consumer under the head of mental
agony and suffering, by applying the principle of Administrative Law,
where the seller being a statutory authority acts negligently,
arbitrarily or capriciously.
(e) Where an alternative
plot/flat/house is allotted and delivered, not at the original agreed
price, but by charging current market rate which is much higher, the
allottee will be entitled to interest at a reasonable rate on the amount
paid towards the earlier allotment, from the date of deposit to date of
delivery of the alternative plot/flat/house. In addition, he may be
entitled to compensation also, determined with reference to the facts of
the case, if there are no justifiable reasons for non-delivery of the
first allotted plot/flat/house.
(f) Where the plot/flat/house has
been allotted at a tentative or provisional price, subject to final
determination of price on completion of the project (that is acquisition
proceedings and development activities), the Development Authority will
be entitled to revise or increase the price. But where the allotment is
at a fixed price, and a higher price or extra payments are illegally or
unjustifiably demanded and collected, the allottee will be entitled to
refund of such excess with such interest, as may be determined with
reference to the facts of the case.
(g) Where full payment is made and
possession is delivered, but title deed is not executed without any
justifiable cause, the allottee may be awarded compensation, for
harassment and mental agony, in addition to appropriate direction for
execution and delivery of title deed.
(h) Where the allotment relates to a
flat/house and construction is incomplete or not in accordance with the
agreed specifications, when it is delivered, the allottee will be
entitled to compensation equivalent to the cost of completing the
building or rectifying the defects.
(i) The quantum of compensation to be awarded, if it is to be awarded,
will depend on the facts of each case, nature of harassment, the period
of harassment and the nature of arbitrary or capricious or negligent
action of the authority which led to such harassment.
(j) While deciding whether the
allottee is entitled to any relief and in moulding the relief, the
following among other relevant factors should be considered : (i)
whether the layout is developed on 'no profit no loss' basis, or with
commercial or profit motive; (ii) whether there is any assurance or
commitment in regard to date of delivery of possession; (iii) whether
there were any justifiable reasons for the delay or failure to deliver
possession; (iv) whether the complainant has alleged and proved that
there has been any negligence, shortcoming or inadequacy on the part of
the developing authority or its officials in the performance of the
functions or obligations in regard to delivery; and (v) whether the
allottee has been subjected to avoidable harassment and mental agony.
Whether Respondent is entitled to
interest?
11. At the outset, we may notice
that there is some vagueness in the order of the Commission, in regard
to the period for which interest is awarded. The Commission has awarded
interest at the rate of 18% per annum commencing from the expiry of two
years after the deposit of 'last instalment' of Rs.53 lakhs. The sum of
Rs.53 lakhs was not paid in instalments as assumed by the Commission.
BDA recovered Rs.54,16,075/- due towards the cost of 15 HIG Houses by
adjustment and appropriation from the amount which had became refundable
to the Respondent on account of surrender of allotment in regard to LIG
units. Such adjustment was made on 15.5.1989 and for all purposes, that
is the date of payment of price of the HIG Houses. As the houses were
delivered in January/March, 1997, the direction issued by the Commission
would mean that BDA had to pay interest at the rate of 18% per annum
from 15.5.1991 to January/March, 1997 which works out to about Rs.55
lakhs. Because of the vagueness in the direction regarding date of
commencement of interest, the Respondent contended that interest should
be calculated from the expiry of two years from the date of payment of
last instalment, which was in December, 1985 (which was in respect of
LIG units). Respondent contends that if interest is so calculated the
amount due as interest would be Rs.87.89 lakhs. Be that as it may.
2. The Commission has neither
referred to the relevant facts nor drawn proper inferences. There is no
basis for the finding that BDA had agreed to deliver the houses by
December, 1986 or the finding that no reason was shown for the delay in
delivery. The allotment of 15 HIG Houses identified by House numbers was
only by resolution dated 16.1.1987 and communicated to Respondent on
27.5.1987. The payment was only on 15.5.1989. Delivery could not,
therefore, obviously be by the end of December, 1986. If reasonable
period for construction is to be reckoned as two years (as assumed by
the Commission), then the question of delay would arise only after
15.5.1991. The Commission also assumed that mere delay automatically
meant deficiency in service and in all such cases, the allottee will be
entitled to interest at 18% per annum from the date of payment till date
of delivery by relying on its decision in HUDA vs. Darsh Kumar. The
decision of the Commission in HUDA vs. Darsh Kumar was held to be
unsustainable by this Court, on appeal in HUDA vs. Darsh Kumar [2005 (9)
SCC 449]. This Court held that there cannot be uniform award of interest
at 18% per annum in all cases and that in cases of complaints of
deficiency in service by a development authority relating to allotment
of plots/flats, the principles laid down in Balbir Singh (Supra) should
be applied. Therefore, the decision of the Commission under appeal,
based on its earlier decision in Darsh Kumar, cannot be sustained.
13. As already noticed, where the
grievance is one of delay in delivery of possession, and the Development
Authority delivers the house during the pendency of the complaint at the
agreed price, and such delivery is accepted by the allottee-complainant,
the question of awarding any interest on the price paid by him from the
date of deposit to date of delivery of possession, does not arise. The
allottee who had the benefit of appreciation of price of the house, is
not entitled to interest on the price paid. In this case, the 11 houses
were delivered in 1997 at the agreed prices (Rs. 5.5 lacs per corner HIG
House and Rs.4.75 lacs per other HIG Houses). In view of it, the order
of the Commission awarding interest at 18% per annum on the price of the
houses is unsustainable and liable to be set aside.
Whether respondent is entitled to
any compensation?
14. This leads us to the next
question as to whether the Respondent is entitled to any compensation,
to make good the loss caused to him on account of the delay in delivery.
The loss is the rental income which the houses would have fetched if
they had been delivered earlier from the agreed due date to date of
actual delivery of possession. Alternatively, it is the rent paid by the
Respondent for the houses taken on lease due to non-availability of the
allotted houses. The Respondent contends that it is entitled to
reimbursement of the rents paid by it in respect of 11 houses, on
account of the delay on the part of BDA in delivering the houses. It was
submitted that even if a reasonable time of two years is provided for
construction from the deemed date of payment (15.5.1989), BDA would be
liable to compensate the Respondent for the rent paid by it for 11
houses from 15.5.1991 till January/March, 1997. Respondent alleged that
it had to pay a rent of Rs.3000/- per house or Rs.33000/- for 11 Houses,
per month, due to the non-delivery of 11 HIG Houses. The Respondent
submitted that the compensation payable would therefore be around Rs.23
lakhs; and that as it had restricted its claim to Rs.16,50,000/- in the
complaint under this head, the said amount may be awarded as
compensation.
15. The Respondent did not produce
any document to show that it paid Rs.3,000/- per month per house for
similar houses between 1991 and 1997. Nor did it produce any evidence to
show that Rs.3000/- was the prevailing rent for similar houses. It is
not the case of the Respondent that documentary evidence for payment of
rent was not available. Where documentary evidence was available, but
not produced, obviously a mere statement in the affidavit cannot be the
basis for award of damages.
16. The more serious issue is
whether the facts and circumstances warrant a finding of negligence and
deficiency in service on the part of BDA necessitating award of
compensation. The brochure relating to the BDA scheme did not mention
any specific date for delivery of possession of the houses. No agreement
was entered into between the parties stipulating any time for
performance or delivery of houses.
The only document on which reliance
is placed by the respondent is a letter dated 22.8.1985 wherein BDA
makes a reference to the expected date of completion of construction
while intimating the revised cost of the HIG houses on account of
escalation etc. The said letter stated that the total cost of 15 HIG
houses would be Rs.7125000/- and after adjustment of Rs.1068750/-, the
balance of Rs.6036250/- was payable in seven bi-monthly instalments from
November, 1985 to December, 1986, (the first six instalments being
Rs.862327/- and the last instalment being Rs.862288/-). It also
incidentally stated that the houses would be ready for occupation in
December, 1986. The instalments were not paid and respondent itself was
the defaulter. Nevertheless, BDA allotted 15 houses as per intimation
dated 27.5.1987. In a self financing scheme, the instalments paid by the
allottees are used for construction. If an allottee does not pay the
instalments, he cannot obviously expect completion of construction. In
this case, the payment was received by BDA (without charging any
interest) by way of adjustment on 15.5.1989.
Even if the reasonable period for
construction is taken as two years, BDA had to explain the 'delay' only
from 15.5.1991 and not from 1985 as assumed by the Commission. BDA
delivered four houses in time, that is in 1989 and 1990. It did not
deliver the remaining 11 houses, as its contractor delayed execution of
the work. It may be mentioned that the project contemplated construction
of 558 HIG houses and the work got stuck only in regard to 68 houses
(including the 11 houses to be delivered to the Respondent). When the
respondent wrote letters in 1989, 1990, 1993 and 1994 and also got in
touch with BDA officers, seeking possession, BDA explained that the
delay was on account of its contractor (M/s Khoday Engineering) stopping
work and raising a dispute. BDA took necessary steps, and even sought
government intervention, to persuade the contractor to proceed with the
work. Having failed in its effort, it ultimately cancelled the contract
with the contractor and got the work completed through an alternative
agency and immediately after completion, delivered the houses in
January/March, 1997.
17. We find that both parties - BDA as also the Respondent proceeded on
the basis that time was not the essence of the contract. In a contract
involving construction, time is not the essence of the contract unless
specified. Even when the respondent wrote the letters dated 29.11.1989,
17.1.1990, 9.7.1993 and 11.1.1994, it did not make time for performance
the essence of contract, nor fix any reasonable time for performance.
The Respondent did not also choose
to terminate the contract, obviously in view of the manifold increase in
the value of the Houses. For the first time, by notice dated 11.7.1994,
it purported to make the time the essence, but demanded delivery within
an unreasonable period of one month and filed the complaint on 4.2.1995.
Thus, it cannot be said that the Respondent made time the essence of
contract, in a manner recognized in law. We also find that the
development authority was constructing these houses under a
self-financing scheme on 'No-Profit No-Loss basis' by using the
instalments/amounts paid by the allottees. The houses were delivered in
1997 at a price agreed in 1986. By 1997, the value had gone up many
times (more than 10 times according to BDA). The Respondent had the
benefit of such rise in value. The respondent also failed to prove any
negligence on the part of BDA. In this factual background, we find it
difficult to hold that there was 'deficiency in service' on the part of
BDA entitling the respondent for any compensation by way of interest or
otherwise. Consequently, the respondent is not entitled to any
compensation.
18. We may also note that the
respondent had also written letters dated 27.12.2005 and 25.1.2006
during the pendency of these appeals stating that if the sale deeds were
executed in respect of these 11 houses, it will withdraw its claim
against BDA. The sale deeds were not executed and the matter is kept
pending in view of the pendency of the dispute.
Conclusion
19. Before concluding, it is necessary to refer to one more contention
urged by BDA. It contended that when a person enters into a contract for
purchasing a house (land with building), from a Development Authority,
the allottee does not 'hire or avail of a service' and is not a
'consumer' under the Act. It is contended that where the contract is for
sale of a house (land with building) as contrasted from a contract for
construction of a house by a contractor with the site-owner, the seller
is not a service provider, and the purchaser is not a consumer; and sale
of land with a building constructed by a development authority, involves
neither sale of goods, nor hiring/availing of any services. BDA had
specifically raised this contention before the Commission as a
preliminary objection regarding maintainability of the complaint. It
appears that this contention was not pressed before the Commission nor
raised as a specific ground in the special leave petition, in view of
the decision of this Court in Lucknow Development Authority vs. M. K.
Gupta (Supra). In that case, a two-Judge Bench of this Court held that
where a development authority undertakes to construct buildings or allot
houses or building sites either as amenity or as benefit, it amounts to
rendering of a service and will be covered by the expression 'service
made available to potential users' referred to in section 2(o) of the
Act. But this Court did not examine or deal with the question whether a
contract for sale of a house premises, (that is site with a constructed
house), as contrasted from a contract of construction amounted to
'providing a service of any description to a potential user including
housing construction'. Be that as it may. Though there appears to be
some logic in the contention of BDA, we do not propose to decide the
issue, as we are allowing this appeal on other grounds, and as this
contention was not specifically pressed before the Commission. We leave
this question open for decision in an appropriate case.
20. In view of the above, we allow
this appeal and set aside the order dated 11.4.2002 of the National
Consumer Disputes Redressal Commission. As the main prayer for
completion and delivery of the houses was complied with during the
pendency of the complaint, and as we have held that respondent is not
entitled to interest or compensation, the complaint is disposed of with
a direction to BDA to complete the process of execution and registration
of sale deed/s in respect of the houses without claiming any extra cost,
within three months from today. The cost of stamp duty and registration
in respect of such sale deeds will be borne by the respondent. Parties
to bear their respective costs.
Print This Judgment
|