Judgment:
Arising Out of S.L.P. (C) NO.14804 OF 2005 With CIVIL APPEAL NO. 1100 OF
2007 (Arising out of S.L.P.(c) No.12954 of 2005)
A.K.Mathur, J.
- Leave granted.
Since the question of law involved
in both the appeals is common, they are disposed of by this common
judgment. For the sake of convenience, the facts stated in Civil Appeal
arising out of S.L.P.(c) No.14804 of 2005 are taken into consideration.
This appeal is directed against the
order passed by learned Single Judge of the Gauhati High Court, Itanagar
Bench in Writ Petition No.408 of 2004 whereby learned Single Judge set
aside the order dated 15.9.2004 passed by the Deputy Commissioner cum
District Judge, Papum Pare, District, Yupia in Miscellaneous Application
No.10 of 2004 condoning the delay in making application under Section 34
of the Arbitration and Conciliation Act, 1996 (hereinafter to be
referred to as 'the Act' ), being not maintainable. Hence, the order
dated 15.9.2004 was set aside and the writ petition was allowed.
Aggrieved against this order passed by the High Court of Gauhati,
Itanagar Bench, State of Arunachal Pradesh has preferred the present
appeal.
Brief facts which are necessary for
disposal of this appeal are that the respondent herein entered into a
contract agreement bearing No.DD/03 of 1992-93 with the State of
Arunachal Pradesh in Public Works Department for executing the
contractual work of construction of road bridges. The value of the work
in question although was initially fixed at Rs.77.43 lakhs but on the
basis of the post tender negotiation by and between the parties, the
price of the work was re-fixed at Rs.1.15 crores. The work was to be
completed within two calendar years from the date of commencement of the
work. The work commenced on 10.4.1993 and it was completed in March,
1999. According to the petitioner-respondent herein the delay in
execution of the work was due to deviation from the original scope of
work and several obstructions and difficulties including delay in
approval of the design and drawings and also in making payment against
running accounts bills from time to time. The respondent herein raised
bill for the contractual work which according to the respondent was
refused to be paid due to certain arbitrary and untenable reasons. Such
refusal gave rise to a dispute and accordingly, need arose for
arbitration. The respondent then approached the Court under section
11(6) of the Act which was numbered and registered as Arbitration Case
No.21 of 2000 and the same was disposed of by the High Court appointing
an arbitrator to adjudicate the dispute between the parties. One
arbitrator was appointed on 18.10.2001 but subsequently that arbitrator
was changed by the present arbitrator. On 12.10.2003 the arbitrator
passed an interim award awarding Rs.65,52,878/- with simple interest to
be calculated if the award amount was not paid within 60 days from the
date of the award. However, the period of limitation prescribed under
Section 34 (3) of the Act for setting aside the award expired in the
meantime. The appellant then wrote a letter to the arbitrator for review
of the award and also sought clarification in respect of the award on
2.4.2004. On 10.4.2004 the arbitrator by his letter stated that he had
no jurisdiction to entertain the request for review of the award and
also informed that the award dated 12.10.2003 was in fact a final award
pertaining to the issues involved. On 21.6.2004 the respondent-
petitioner filed an application for execution of the interim award dated
12.10.2003 before the Deputy Commissioner. On 6.8.2004 the appellant
filed an application under Section 34 of the Act for setting aside the
award dated 12.10.2003 together with an application under Section 5 of
the Limitation Act read with Section 34(3) of the Act for condonation of
delay in filing the application for setting aside the award. The said
application was entertained and was fixed for hearing on condonation of
delay after 15 days. Aggrieved against this order, a writ petition was
filed by the respondent herein but the same was disposed of by the High
Court with the observation that as the matter was pending before the
court below it would not be appropriate to interfere at this stage and
left the Deputy Commissioner to decide the matter. The Deputy
Commissioner, Papum Pare, Itanagar by the impugned order dated 15.9.2004
decided the application condoning the delay in preferring the
application under Section 34 of the Act by the appellant. Aggrieved
against this order, the present writ petition was filed by the
respondent herein. It is the legality of this order which was challenged
before the High Court. Learned Single Judge of the High Court after
hearing both the parties came to the conclusion that the order passed by
the Deputy Commissioner in condoning the delay was not correct and it
took the view that under section 34 of the Act, there was a delay of
seven months from the date of first order and a delay of six months from
the date of second order.
The plea of the appellant- State
before the court below was that the award was passed on 12.10.2003 and a
copy was received on 23.10.2003. As such, the period of limitation
started from 23.10.2003. Since the letter was sent by the appellant to
the arbitrator on 2.4.20043 for review of the award and a reply thereof
was received on 10.4.2004 whereby the matter was clarified by the
arbitrator, therefore, the cause of action accrued in favour of the
appellant on 10.4.2004 and application under Section 34 of the Act was
filed on 6.8.2004 i.e. within three months and the extended period of
one month, therefore, it was within limitation. Though this contention
prevailed before the trial court but the same failed before the High
Court on the ground that the cause of action accrued to the appellant on
23.10.2003 when the appellant received the copy of the award and the
letter which was written on 2.4.2004 was totally misconceived. The
interim award was final with regard to the claims raised therein,
therefore, the whole exercise undertaken by the appellant was totally
misconceived. Hence, learned Single Judge allowed the writ petition and
set aside the order of the trial court. Aggrieved against this order
passed by the learned Single Judge, the present appeal was filed.
We have heard learned counsel for
the parties and perused the record. Learned counsel for the appellant
tried to persuade us that in fact the cause of action has arisen to the
appellant on 10.4.2004 when the letter was received from the arbitrator
and therefore, the appellant was entitled to count the period of
limitation from the date of receipt of the letter from the arbitrator
and if the limitation was to start from 10.4.2004 then the appellant has
a right to move an application for setting aside of the award under
section 34 of the Act within three months and the extended period of one
month and the appellant having filed the application on 6.8.2004,
therefore, it was within time. The submission of learned counsel for the
appellant is totally misconceived and it cannot be accepted. A perusal
of the interim award passed by the arbitrator clearly shows that it was
final to the extent of the claims decided therein and it may be relevant
to refer to the concluding portion of the award which reads as under :
" I further direct that the awarded
amount is indicated above along with the interest, wherever shown till
the date of interim award amounting to Rs.65,52,878.00 (Rupees Sixty
five lakhs fifty two thousand Eight hundred seventy eight only), shall
be paid by the Respondents to the Claimant within 60 days from the date
of the award, failing which a simple interest on the unpaid amount @ 18%
(Eighteen percent) per annum shall be payable to the Claimant by the
respondents after 60 days of this interim award."
Therefore, this interim award which
did not mince any word and determined the amount after discussing the
claims in detail and finally calculated the amount under each of the
claims. Therefore, there was no confusion in this award. It was
absolutely thoughtlessness on the part of the appellant to have written
a letter after six months i.e. on 2.4.2004 seeking review of the interim
award to the following effect:
" While submitting the request for
review the case, it is also requested that your honour may kindly
consider (sic.) the following points regarding mode of payments, if at
all, the payment is to be made, as the award given by your honour is for
the interim payment.
(a) Whether payment is to be made
directly to M/s. Damani Construction Co. or through honourable court.
(b) In case, the payment is to be
made directly to M/s.Damani Construction Co., an equivalent Bank
Guarantee Bond from any Nationalized Bank shall be required from the
Contractor since it will be an interim payment and final verdict
awaited.
Submitted for your kind
consideration please."Firstly, the letter had been designed not strictly
under section 33 of the Act because under Section 33 of the Act a party
can seek certain correction in computation of errors, or clerical or
typographical errors or any other errors of a similar nature occurring
in the award with notice to the other party or if agreed between the
parties, a party may request the arbitral tribunal to give an
interpretation of a specific point or part of the award. This
application which was moved by the appellant does not come within any of
the criteria falling under Section 33(1) of the Act. It was designed as
if the appellant was seeking review of the award. Since the Tribunal had
no power of review on merit, therefore, the application moved by the
appellant was wholly misconceived. Secondly, it was prayed whether the
payment was to be made directly to the respondent or through the Court
or that the respondent might be asked to furnish Bank guarantee from a
nationalized Bank as it was an interim award, till final verdict was
awaited. Both these prayers in this case were not within the scope of
Section 33. Neither review was maintainable nor the prayer which had
been made in the application had anything to do with Section 33 of the
Act. The prayer was with regard to the mode of payment. When this
application does not come within the purview of Section 33 of the Act,
the application was totally misconceived and accordingly the arbitrator
by communication dated 10.4.2004 replied to the following effect.
" However, for your benefit I may
mention here that as per the scheme of the Act of 1996, the issues/
claims that have been adjudicated by the interim award dated 12.10.2003
are final and the same issues cannot be gone into once again at the time
of passing the final award."
Therefore, the reply given by the
arbitrator does not give any fresh cause of action to the appellant so
as to move an application under Section 34 (3) of the Act. In fact, when
the award dated 12.10.2003 was passed the only option with the appellant
was either to have moved an application under Section 34 within three
months as required under sub-section (3) of Section 34 or within the
extended period of another 30 days. But in stead of that a totally
misconceived application was filed and there too the prayer was for
review and with regard to mode of payment. The question of review was
totally misconceived as there is no such provision in the Act for review
of the award by the arbitrator and the clarification sought for as to
the mode of payment is not contemplated under Section 33 of the Act.
Therefore, in this background, the application was totally misconceived
and the reply sent by the arbitrator does not entitle the appellant a
fresh cause of action so as to file an application under Section 34(3)
of the Act, taking it as the starting point of limitation from the date
of reply given by the arbitrator i.e. 10.4.2004.
Thus, in this background, the view
taken by learned Single Judge appears to be justified and there is no
ground to interfere in this appeal. Consequently, there is no merit in
both the appeals and the same are dismissed with no order as to costs.
Print This Judgment
|