Judgment:
SPECIAL LEAVE PETITION (Civil) NO.2426 OF 2007
R V Raveendran, J.-
Leave granted
CThe petitioner (Punjab Urban
Planning & Development Authority 'PUPDA' for short) allotted Site No.SCF
83 in Mohali in favour of the respondents, on acceptance of their bid of
Rs.15,10,000/- for the said site at an auction held on 10th August,
1994. The letter of allotment dated 29.5.1995 took note of payment of
Rs.3,77,500/- (payment of 25% of the price) and permitted the
respondents to pay the balance of Rs.1132500/- towards price and
Rs.283125/- towards interest upto 10.8.1998 at 10% per annum, in four
equated instalments on 10.8.1995, 10.8.1996, 10.8.1997 and 10.8.1998.
The letter of allotment required PUPDA to deliver the possession of the
site to the allottee within three months.
2. The Estate Officer of PUPDA made
an order dated 21.7.1997 resuming the site on the ground that the
respondents had failed to pay the instalments. The respondents
challenged the order of resumption before the Appellate Authority
contending that they could not pay the instalments, as PUPDA had not
delivered possession of the site. To show their bona fides they sought
the permission of the Appellate authority to deposit Rs.1415625/- being
the balance of price and interest, in terms of the letter of allotment.
On such permission being granted, the respondents deposited the said
amount on 16.8.2001. The Appellate Authority by order dated 13.12.2001
set aside the resumption order and restored the allotment of the site in
favour of the respondents and directed the Estate Officer to inform them
about the amount of interest/penalty payable in respect of the delayed
payments.
3. The respondents challenged the
order of Appellate Authority in revision. The Revisional Authority by
order dated 26.8.2003 held that the respondents were not liable to pay
any interest/penalty for the period when possession was not delivered.
He directed the Estate Officer to deliver the site to the respondent and
reschedule the instalments from the date when possession was handed
over. In pursuance of the said order, possession was delivered to the
respondents on 6.1.2004. The said order was belatedly challenged by the
PUPDA before the High Court in the year 2006. The High Court has
rejected the writ petition as having no merit.
4. Learned counsel for the
petitioner submitted that the resumption order was quashed on a wrong
assumption that the site in question was under some dispute with a
Gurudwara and PUPDA was not in a position to deliver the site as per
letter of allotment; that the dispute with the Gurudwara was sorted out
prior to the auction sale and as on the date of the auction sale and the
due date for delivery of possession, there was no pending dispute and no
impediment for delivery and the non-delivery was only on account of
respondents failing to take possession; and that long thereafter there
was some encroachment which was solely on account of respondents not
taking possession and committing breach; and that therefore there was no
infirmity in the order for resumption.
5. We find no merit in the
contention of the petitioner. The appellate authority had also set aside
the cancellation of allotment and had directed restoration of the site
to the respondents and that order was not challenged by PUPDA and
attained finality. It was respondents who challenged the order of the
appellate authority before the revisional authority, being aggrieved by
the direction for payment of interest and penalty. We do not propose to
interfere with the concurrent finding of the appellate authority,
revisional authority and the High Court directing restoration of the
site to the respondents.
6. Learned counsel for the
petitioner next contended that the authority is entitled to interest at
10% P.A. and penalty from 11.8.1998 up to the date of payment. It was
submitted that interest was paid only up to 10.9.1998 and interest for
the balance period that is 11.8.1998 to 16.8.2001 (date of payment) was
not paid. On the other hand learned counsel for the respondents
submitted that the respondents had paid the full price as also
Rs.2,83,125/- towards interest on 16.8.2001 itself, even though the
possession of the site was delivered to them only on 6.1.2004; and that
as per the order of the revisional authority, affirmed by the High
Court, the respondents are not liable to pay interest or penalty for the
period during which possession was not handed over to them, and as
possession was delivered only on 6.1.2004 long after full payment on
16.8.2001, PUPDA was itself liable to refund the amount paid by
Respondents towards the interest and also pay interest to respondents on
the value of the site from 16.8.2001 to 6.1.2004. But the learned
counsel for respondents submitted on instructions, that the respondents
were not interested in seeking refund of any amount from PUPDA and were
only interested in the long pending issue being closed.
7. In view of the above, it is
unnecessary to examine the claim regarding interest. The petition is
disposed of by recording the submission of the respondents that they
will not press for refund of any part of amount paid towards interest or
otherwise from PUPDA. It is needless to say that PUPDA shall convey the
allotted site to the respondents on fulfillment of the required
formalities. Parties to bear respective costs.
Print This Judgment
|